  • Updates for Riverview Junior High School Project
    Naylor, Wentworth, Lund Architects, Hughes Construction, BDK (owner representative), and the Murray City School District are actively collaborating on the planning and development of the Riverview Junior High School rebuild. Below is a timeline outlining the progress made so far and the next steps in the process.  The new building is scheduled for completion in the spring/summer of 2027, and students will occupy the spaces in August 2027 for the 2027-2028 school year.

    • 12/16/2024 – 50% construction documents sent out for review
    • 12/30/2024 – Transformer procured through Murray City Power
    • 1/15/2025 – 50% construction document estimate completed
    • 1/16/2025 – Switchgear procurement initiated
    • 1/15/2025 through 1/30/2025 – BDK reviewing 50% construction estimate from Hughes Construction
    • 2/17/2025 – Bid package #2 to be issued (earthwork, partial demolition, steel, masonry, footings/foundations, site utilities, asphalt paving, site concrete)
    • 3/6/2025 – Bid package #2 bids due
    • 3/15/2025 – Hughes Construction and BDK complete bid package #2 review and recommend approval
    • March 2025 – 100% construction documents complete
    • April 2025 – Board approval for bid package #2 complete
    • April 2025 – Hughes Construction mobilization and construction start for bid package #2
    • April 2025 – 100% construction document bidding
    • End of April 2025 – BDK/Hughes complete guaranteed maximum price for the balance of the project
    • May 2025 – MCSD/BDK review and recommendation to approve
    • Mid-June 2025 – Final approval and continuation of the project

    Updates for Murray High School Project
    VCVO Architects, Hogan Construction, BDK (owner representative), and the Murray City School District are actively collaborating on the planning and development of the Murray High School expansion. Below is a timeline outlining the progress made so far and the next steps in the process.  The new addition is scheduled for completion in the spring/summer of 2027, and students will occupy the spaces in August 2027 for the 2027-2028 school year.

    • 1/13/2025 – 100% bid document check set issued
    • 1/13/2025 through 1/21/2025 – BDK and Hogan Construction review bid documents
    • 1/27/2025 – 100% construction documents finalized
    • 1/28/2025 – 100% construction documents sent out to bid
    • 2/18/2025 – Bids due
    • 2/25/2025 – Guaranteed maximum price finalization by Hogan, BDK, and MCSD
    • End of February 2025 – Board review and approval
    • March-May 2025 – Submittals, planning, permits, and preparation for construction
    • June 2025 – Construction begins
  • On behalf of the Murray City School District, we would like to express our sincere gratitude for the community support in the recent bond election. Your vote will have a significant impact on the future of our schools and our community.

    With the bond’s approval, we will:

    • Rebuild Riverview Junior High School: Providing our students with a safe, modern, and 21st-century learning environment.
    • Expand and Enhance Murray High School: Adding a classroom wing and upgrading security to ensure continuity for grades 9–12, with a focus on graduation pathways and opportunities for all high school students.

    Both projects are scheduled for completion in the spring/summer of 2027, and students will occupy the new spaces in August 2027.  

    We are deeply thankful to voters for partnering with the district to support future generations. Your investment in our schools is an investment in our children’s future, and we are committed to using these funds responsibly and transparently. For ongoing updates, please visit our website. 

    Thank you again for placing your trust in us. We look forward to working together to build a bright future for Murray City.

    Jennifer Covington – Superintendent
    Jaren Cooper – Board of Education President

  • October 23, 2024

    Will Murray City build ‘Riverview Jr. High? It’s up to the voters (Deseret News)

    October 17, 2024 Audio from final pubic hearing on October 17, 2024 October 15, 2024

     

    October 14, 2024 Link to KUTV story October 7, 2024 A Message from Superintendent Jennifer Covington Explaining the Details of this Year's Bond Measure Proposal October 3, 2024 Voter Information Pamphlet - All Registered Voters in Murray Receive a copy of this pamphlet (mailed the week of October 7)

  • Click here for a downloadable FAQ

    The Murray City community thrives on strong schools that provide a solid education foundation for children.  The Murray City School District (MCSD) will propose a general obligation bond measure to voters on the November 2024 ballot to rebuild Riverview Junior High School and add a classroom wing to Murray High School.

    [sp_easyaccordion id="25875"]

    June 3, 2024
    Murray City School District Procedure for Election Campaign Ethics

  • The Murray Board of Education voted to select two architect firms: Naylor Wentworth Lund to provide design services for the Riverview Jr. High rebuild, and VCBO to provide design services for Murray High School addition.

  • The Murray Board of Education unanimously approved three actions:

    1. The small boundary adjustment proposed on January 11, 2024 (beginning 2024-25 school year);
    2. Intent to pursue a bond measure to fund two construction projects: An addition to Murray High School and a rebuild of Riverview Jr. High School (estimated to be complete 2027-28) ; and
    3. Grade reconfiguration, moving all sixth grade students up to secondary schools and all ninth grade students up to high school; this shifts the District from offering a jr. high school model to a middle school model (estimated to be complete 2027-28)